N84 Grid

Cheshire Connection Node A 400kV Substation

NESO connection site, host NGET.

Contracted here5.13 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Oct 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue5,130 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lightsource Lower Frankton31 May 202430 Oct 2037240 MW
Bute Hydrogen Project 631 May 202430 Oct 20373,600 MW
New Marton Solar Farm - PVDP31 May 202430 Oct 2037780 MW
Noventum -New Marton20 Dec 202430 Oct 2037510 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2037: 5.1 GW20375.1 GW
0 MW4.0 GW8.0 GW2037: 5.1 GW20375.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20375,130 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lightsource Lower Frankton240 MW0 MW30 Oct 20371gate 1Scoping
2Bute Hydrogen Project 63,600 MW240 MW30 Oct 20371gate 1Scoping
3New Marton Solar Farm - PVDP780 MW3,840 MW30 Oct 20371gate 1Scoping
4Noventum -New Marton510 MW4,620 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203745,130 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bute Hydrogen Project 6Gas3,600 MW30 Oct 2037Scoping
New Marton Solar Farm - PVDPHybrid780 MW30 Oct 2037Scoping
Noventum -New MartonHybrid510 MW30 Oct 2037Scoping
Lightsource Lower FranktonHybrid240 MW30 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.