The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Lightsource Lower Frankton
31 May 2024 to 30 Oct 2037 (gate 1) - Bute Hydrogen Project 6
31 May 2024 to 30 Oct 2037 (gate 1) - New Marton Solar Farm - PVDP
31 May 2024 to 30 Oct 2037 (gate 1) - Noventum -New Marton
20 Dec 2024 to 30 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Lightsource Lower Frankton | 31 May 2024 | 30 Oct 2037 | 240 MW |
| Bute Hydrogen Project 6 | 31 May 2024 | 30 Oct 2037 | 3,600 MW |
| New Marton Solar Farm - PVDP | 31 May 2024 | 30 Oct 2037 | 780 MW |
| Noventum -New Marton | 20 Dec 2024 | 30 Oct 2037 | 510 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2037 | 5,130 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Lightsource Lower Frankton | 240 MW | 0 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 2 | Bute Hydrogen Project 6 | 3,600 MW | 240 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 3 | New Marton Solar Farm - PVDP | 780 MW | 3,840 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 4 | Noventum -New Marton | 510 MW | 4,620 MW | 30 Oct 2037 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2037 | 4 | 5,130 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Bute Hydrogen Project 6 | Gas | 3,600 MW | 30 Oct 2037 | Scoping |
| New Marton Solar Farm - PVDP | Hybrid | 780 MW | 30 Oct 2037 | Scoping |
| Noventum -New Marton | Hybrid | 510 MW | 30 Oct 2037 | Scoping |
| Lightsource Lower Frankton | Hybrid | 240 MW | 30 Oct 2037 | Scoping |
Supported by National Energy SO Open Data