N84 Grid

Chesterfield 400kV Substation (Not yet constructed)

NESO connection site, host NGET.

Contracted here0.66 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue657 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Chesterfield31 May 2024 to 30 Oct 2032 (gate 1)
  • Arkwright31 May 2024 to 30 Oct 2034 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Chesterfield31 May 202430 Oct 2032600 MW
Arkwright31 May 202430 Oct 203457 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2032: 600 MW2034: 657 MW203220332034657 MW
0 MW400 MW800 MW2032: 600 MW2034: 657 MW203220332034657 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2032600 MW
2034657 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Chesterfield600 MW0 MW30 Oct 20321gate 1Scoping
2Arkwright57 MW600 MW30 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20321600 MW
2034157 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ChesterfieldHybrid600 MW30 Oct 2032Scoping
ArkwrightBattery storage57 MW30 Oct 2034Scoping

Supported by National Energy SO Open Data