N84 Grid

Chickerell 400kV Substation

NESO connection site, host NGET.

Contracted here3.45 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,450 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Chickerell Solar PV & BESS31 May 202431 Oct 2028400 MW
BESS North Farm31 May 20241 Nov 2031150 MW
Portwind31 May 20246 Dec 20362,500 MW
Chickerell31 May 20246 Dec 2036200 MW
Chickerell31 May 202431 Oct 2037100 MW
Chickerell31 May 202431 Oct 2038100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 400 MW2031: 550 MW2036: 3.3 GW2037: 3.4 GW2038: 3.5 GW2028203020322034203620383.5 GW
0 MW2.0 GW4.0 GW2028: 400 MW2031: 550 MW2036: 3.3 GW2037: 3.4 GW2038: 3.5 GW20282031203420383.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028400 MW
2031550 MW
20363,250 MW
20373,350 MW
20383,450 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Chickerell Solar PV & BESS400 MW0 MW31 Oct 20282gate 2Consents Approved
2BESS North Farm150 MW400 MW1 Nov 20311gate 1Scoping
3Portwind2,500 MW550 MW6 Dec 20361gate 1Scoping
4Chickerell200 MW3,050 MW6 Dec 20361gate 1Awaiting Consents
5Chickerell100 MW3,250 MW31 Oct 20371gate 1Awaiting Consents
6Chickerell100 MW3,350 MW31 Oct 20381gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281400 MW
20311150 MW
203622,700 MW
20371100 MW
20381100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
PortwindHybrid2,500 MW6 Dec 2036Scoping
Chickerell Solar PV & BESSBattery storage400 MW31 Oct 2028Consents Approved
Chickerell (ENSO GREEN HOLDINGS LIMITED)Hybrid400 MW31 Oct 2038Awaiting Consents
BESS North FarmBattery storage150 MW1 Nov 2031Scoping
Chickerell (SSE GENERATION LIMITED)Gas47 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.