The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Chickerell Solar PV & BESS
31 May 2024 to 31 Oct 2028 (gate 2) - BESS North Farm
31 May 2024 to 1 Nov 2031 (gate 1) - Portwind
31 May 2024 to 6 Dec 2036 (gate 1) - Chickerell
31 May 2024 to 6 Dec 2036 (gate 1) - Chickerell
31 May 2024 to 31 Oct 2037 (gate 1) - Chickerell
31 May 2024 to 31 Oct 2038 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Chickerell Solar PV & BESS | 31 May 2024 | 31 Oct 2028 | 400 MW |
| BESS North Farm | 31 May 2024 | 1 Nov 2031 | 150 MW |
| Portwind | 31 May 2024 | 6 Dec 2036 | 2,500 MW |
| Chickerell | 31 May 2024 | 6 Dec 2036 | 200 MW |
| Chickerell | 31 May 2024 | 31 Oct 2037 | 100 MW |
| Chickerell | 31 May 2024 | 31 Oct 2038 | 100 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2028 | 400 MW |
| 2031 | 550 MW |
| 2036 | 3,250 MW |
| 2037 | 3,350 MW |
| 2038 | 3,450 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Chickerell Solar PV & BESS | 400 MW | 0 MW | 31 Oct 2028 | 2 | gate 2 | Consents Approved |
| 2 | BESS North Farm | 150 MW | 400 MW | 1 Nov 2031 | 1 | gate 1 | Scoping |
| 3 | Portwind | 2,500 MW | 550 MW | 6 Dec 2036 | 1 | gate 1 | Scoping |
| 4 | Chickerell | 200 MW | 3,050 MW | 6 Dec 2036 | 1 | gate 1 | Awaiting Consents |
| 5 | Chickerell | 100 MW | 3,250 MW | 31 Oct 2037 | 1 | gate 1 | Awaiting Consents |
| 6 | Chickerell | 100 MW | 3,350 MW | 31 Oct 2038 | 1 | gate 1 | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2028 | 1 | 400 MW |
| 2031 | 1 | 150 MW |
| 2036 | 2 | 2,700 MW |
| 2037 | 1 | 100 MW |
| 2038 | 1 | 100 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Portwind | Hybrid | 2,500 MW | 6 Dec 2036 | Scoping |
| Chickerell Solar PV & BESS | Battery storage | 400 MW | 31 Oct 2028 | Consents Approved |
| Chickerell (ENSO GREEN HOLDINGS LIMITED) | Hybrid | 400 MW | 31 Oct 2038 | Awaiting Consents |
| BESS North Farm | Battery storage | 150 MW | 1 Nov 2031 | Scoping |
| Chickerell (SSE GENERATION LIMITED) | Gas | 47 MW | not stated | Built |
Supported by National Energy SO Open Data