The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Ludgershall - Bicester Solar Farm PVDP
22 Jul 2025 to 1 Nov 2038 (gate 1) - BF88 Oakley
31 May 2024 to 1 Nov 2038 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Ludgershall - Bicester Solar Farm PVDP | 22 Jul 2025 | 1 Nov 2038 | 500 MW |
| BF88 Oakley | 31 May 2024 | 1 Nov 2038 | 1,000 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2038 | 1,500 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Ludgershall - Bicester Solar Farm PVDP | 500 MW | 0 MW | 1 Nov 2038 | 1 | gate 1 | Scoping |
| 2 | BF88 Oakley | 1,000 MW | 500 MW | 1 Nov 2038 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2038 | 2 | 1,500 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| BF88 Oakley | Hybrid | 1,000 MW | 1 Nov 2038 | Scoping |
| Ludgershall - Bicester Solar Farm PVDP | Hybrid | 500 MW | 1 Nov 2038 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.