Chiltern Connection Node C 400kV Substation

NESO connection site, host NGET.

Contracted here1.50 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Nov 2038Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,500 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ludgershall - Bicester Solar Farm PVDP22 Jul 20251 Nov 2038500 MW
BF88 Oakley31 May 20241 Nov 20381,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2038: 1.5 GW20381.5 GW
0 MW1.0 GW2.0 GW2038: 1.5 GW20381.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20381,500 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ludgershall - Bicester Solar Farm PVDP500 MW0 MW1 Nov 20381gate 1Scoping
2BF88 Oakley1,000 MW500 MW1 Nov 2038not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203821,500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BF88 OakleyHybrid1,000 MW1 Nov 2038Scoping
Ludgershall - Bicester Solar Farm PVDPHybrid500 MW1 Nov 2038Scoping

Supported by National Energy SO Open Data