The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Inch Cape Offshore Wind Farm Platform 1
31 May 2024 to 21 Feb 2026, date already passed (gate 2) - Inch Cape Offshore Wind Farm Platform 2
31 May 2024 to 21 Feb 2026, date already passed (gate 2) - Dolphingstone Farm
31 May 2024 to 31 Oct 2028 (gate 2) - Seagreen Phase 1A
31 May 2024 to 1 Apr 2028 (gate not printed) - Boom Power Seaton Hill Generation HUB
31 May 2024 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Inch Cape Offshore Wind Farm Platform 1 | 31 May 2024 | 21 Feb 2026 | 540 MW |
| Inch Cape Offshore Wind Farm Platform 2 | 31 May 2024 | 21 Feb 2026 | 540 MW |
| Dolphingstone Farm | 31 May 2024 | 31 Oct 2028 | 63 MW |
| Seagreen Phase 1A | 31 May 2024 | 1 Apr 2028 | 500 MW |
| Boom Power Seaton Hill Generation HUB | 31 May 2024 | 31 Oct 2033 | 300 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 1,080 MW |
| 2028 | 1,643 MW |
| 2033 | 1,943 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Inch Cape Offshore Wind Farm Platform 1 | 540 MW | 0 MW | 21 Feb 2026 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Inch Cape Offshore Wind Farm Platform 2 | 540 MW | 540 MW | 21 Feb 2026 | 2 | gate 2 | Under Construction/Commissioning |
| 3 | Dolphingstone Farm | 63 MW | 1,080 MW | 31 Oct 2028 | 2 | gate 2 | Consents Approved |
| 4 | Seagreen Phase 1A | 500 MW | 1,143 MW | 1 Apr 2028 | not stated | gate not printed | Under Construction/Commissioning |
| 5 | Boom Power Seaton Hill Generation HUB | 300 MW | 1,643 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 1,080 MW |
| 2028 | 2 | 563 MW |
| 2033 | 1 | 300 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Inch Cape Offshore Wind Farm Platform 2 | Offshore wind | 540 MW | 21 Feb 2026 | Under Construction/Commissioning |
| Inch Cape Offshore Wind Farm Platform 1 | Offshore wind | 540 MW | 21 Feb 2026 | Under Construction/Commissioning |
| Seagreen Phase 1A | Offshore wind | 500 MW | 1 Apr 2028 | Under Construction/Commissioning |
| Boom Power Seaton Hill Generation HUB | Battery storage | 300 MW | 31 Oct 2033 | Scoping |
| Dolphingstone Farm | Battery storage | 63 MW | 31 Oct 2028 | Consents Approved |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.