N84 Grid

Cockenzie 400/275kV

NESO connection site, host SPT.

Contracted here1.94 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date21 Feb 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,943 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Inch Cape Offshore Wind Farm Platform 131 May 202421 Feb 2026540 MW
Inch Cape Offshore Wind Farm Platform 231 May 202421 Feb 2026540 MW
Dolphingstone Farm31 May 202431 Oct 202863 MW
Seagreen Phase 1A31 May 20241 Apr 2028500 MW
Boom Power Seaton Hill Generation HUB31 May 202431 Oct 2033300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 1.1 GW2028: 1.6 GW2033: 1.9 GW202620272028202920302031203220331.9 GW
0 MW1.0 GW2.0 GW2026: 1.1 GW2028: 1.6 GW2033: 1.9 GW20262028203020331.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20261,080 MW
20281,643 MW
20331,943 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Inch Cape Offshore Wind Farm Platform 1540 MW0 MW21 Feb 20262gate 2Under Construction/Commissioning
2Inch Cape Offshore Wind Farm Platform 2540 MW540 MW21 Feb 20262gate 2Under Construction/Commissioning
3Dolphingstone Farm63 MW1,080 MW31 Oct 20282gate 2Consents Approved
4Seagreen Phase 1A500 MW1,143 MW1 Apr 2028not statedgate not printedUnder Construction/Commissioning
5Boom Power Seaton Hill Generation HUB300 MW1,643 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202621,080 MW
20282563 MW
20331300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Inch Cape Offshore Wind Farm Platform 2Offshore wind540 MW21 Feb 2026Under Construction/Commissioning
Inch Cape Offshore Wind Farm Platform 1Offshore wind540 MW21 Feb 2026Under Construction/Commissioning
Seagreen Phase 1AOffshore wind500 MW1 Apr 2028Under Construction/Commissioning
Boom Power Seaton Hill Generation HUBBattery storage300 MW31 Oct 2033Scoping
Dolphingstone FarmBattery storage63 MW31 Oct 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.