Coddington 400kV Substation

NESO connection site, host NGET.

Contracted here2.24 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Sep 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,240 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Newark BESS31 May 202430 Sep 2033600 MW
Navenby Farm31 May 202430 May 20341,000 MW
Mountain Fen31 May 202430 Sep 2034240 MW
Tyler Hill Bicker Fen31 May 202430 May 2035400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2033: 600 MW2034: 1.8 GW2035: 2.2 GW2033203420352.2 GW
0 MW1.3 GW2.5 GW2033: 600 MW2034: 1.8 GW2035: 2.2 GW2033203420352.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033600 MW
20341,840 MW
20352,240 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Newark BESS600 MW0 MW30 Sep 20331gate 1Scoping
2Navenby Farm1,000 MW600 MW30 May 20341gate 1Scoping
3Mountain Fen240 MW1,600 MW30 Sep 2034not statedgate not printedScoping
4Tyler Hill Bicker Fen400 MW1,840 MW30 May 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20331600 MW
203421,240 MW
20351400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Navenby FarmHybrid1,000 MW30 May 2034Scoping
Newark BESSHybrid600 MW30 Sep 2033Scoping
Tyler Hill Bicker FenBattery storage400 MW30 May 2035Scoping
Mountain FenBattery storage240 MW30 Sep 2034Scoping

Supported by National Energy SO Open Data