The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Glenrothes Hybrid BESS & Solar PV
31 May 2024 to 30 Oct 2031 (gate 1) - Pitkevy BESS
22 Jul 2025 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Glenrothes Hybrid BESS & Solar PV | 31 May 2024 | 30 Oct 2031 | 200 MW |
| Pitkevy BESS | 22 Jul 2025 | 31 Oct 2034 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2031 | 200 MW |
| 2034 | 400 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Glenrothes Hybrid BESS & Solar PV | 200 MW | 0 MW | 30 Oct 2031 | 1 | gate 1 | Scoping |
| 2 | Pitkevy BESS | 200 MW | 200 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2031 | 1 | 200 MW |
| 2034 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Pitkevy BESS | Battery storage | 200 MW | 31 Oct 2034 | Scoping |
| Glenrothes Hybrid BESS & Solar PV | Hybrid | 200 MW | 30 Oct 2031 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.