N84 Grid

Conland Substation

NESO connection site, host SPT.

Contracted here0.40 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue400 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Glenrothes Hybrid BESS & Solar PV31 May 202430 Oct 2031200 MW
Pitkevy BESS22 Jul 202531 Oct 2034200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2031: 200 MW2034: 400 MW2031203220332034400 MW
0 MW200 MW400 MW2031: 200 MW2034: 400 MW2031203220332034400 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031200 MW
2034400 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Glenrothes Hybrid BESS & Solar PV200 MW0 MW30 Oct 20311gate 1Scoping
2Pitkevy BESS200 MW200 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311200 MW
20341200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Pitkevy BESSBattery storage200 MW31 Oct 2034Scoping
Glenrothes Hybrid BESS & Solar PVHybrid200 MW30 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.