Coryton South 400kV Substation

NESO connection site, host NGET.

Contracted here1.00 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Jun 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,000 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Gateway Energy Centre Power Station31 May 202430 Jun 2029450 MW
Gateway Energy Centre Power Station31 May 202430 Oct 2029550 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2029: 1.0 GW20291.0 GW
0 MW500 MW1.0 GW2029: 1.0 GW20291.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20291,000 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Gateway Energy Centre Power Station450 MW0 MW30 Jun 2029not statedgate not printedConsents Approved
2Gateway Energy Centre Power Station550 MW450 MW30 Oct 2029not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202921,000 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Gateway Energy Centre Power StationBattery storage1,000 MW30 Oct 2029Consents Approved
CorytonGas850 MW30 Oct 2029Built

Supported by National Energy SO Open Data