N84 Grid

Cottam 400kV Substation

NESO connection site, host NGET.

Contracted here2.10 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date27 Aug 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,100 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cottam Solar PV + BESS31 May 20241 Sep 2029600 MW
Tillbridge Solar31 May 202427 Aug 2028500 MW
Cottam31 May 202431 Oct 2029250 MW
Cottam31 May 202430 Jul 2030250 MW
Cottam PV & BESS31 May 202431 Oct 2033500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2028: 500 MW2029: 1.4 GW2030: 1.6 GW2033: 2.1 GW2028202920302031203220332.1 GW
0 MW1.3 GW2.5 GW2028: 500 MW2029: 1.4 GW2030: 1.6 GW2033: 2.1 GW20282030203220332.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028500 MW
20291,350 MW
20301,600 MW
20332,100 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cottam Solar PV + BESS600 MW0 MW1 Sep 20292gate 2Consents Approved
2Tillbridge Solar500 MW600 MW27 Aug 2028not statedgate not printedScoping
3Cottam250 MW1,100 MW31 Oct 2029not statedgate not printedConsents Approved
4Cottam250 MW1,350 MW30 Jul 2030not statedgate not printedConsents Approved
5Cottam PV & BESS500 MW1,600 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281500 MW
20292850 MW
20301250 MW
20331500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cottam Solar PV + BESSHybrid600 MW1 Sep 2029Consents Approved
Cottam (GATE BURTON ENERGY PARK LIMITED)Hybrid500 MW30 Jul 2030Consents Approved
Tillbridge SolarHybrid500 MW27 Aug 2028Scoping
Cottam PV & BESSHybrid500 MW31 Oct 2033Scoping
CDCLGas445 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.