Coylton 275kV substation

NESO connection site, host SPT.

Contracted here0.88 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date30 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue582.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Coylton 275kV Greener Grid Park31 May 202418 May 202650 MW
Mount Farm7 Nov 202531 Oct 20262.5 MW
Coylton 275kV Greener Grid Park31 May 202430 Apr 2026100 MW
McQuittiston Farm7 Nov 202529 May 202629.9 MW
Drongan Battery Storage31 May 202431 Oct 2027100 MW
Coylton 275kV Greener Grid Park31 May 202430 Oct 2037300 MW
Coylton Farm31 May 202430 Oct 2037300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2026: 182 MW2027: 282 MW2037: 882 MW202620282030203220342037882 MW
0 MW500 MW1.0 GW2026: 182 MW2027: 282 MW2037: 882 MW20262029203220352037882 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026182.4 MW
2027282.4 MW
2037882.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Coylton 275kV Greener Grid Park50 MW0 MW18 May 20262gate 2Consents Approved
2Mount Farm2.5 MW50 MW31 Oct 20262gate 2Consents Approved
3Coylton 275kV Greener Grid Park100 MW52.5 MW30 Apr 2026not statedgate not printedScoping
4McQuittiston Farm29.9 MW152.5 MW29 May 2026not statedgate not printedScoping
5Drongan Battery Storage100 MW182.4 MW31 Oct 20271gate 1Scoping
6Coylton 275kV Greener Grid Park300 MW282.4 MW30 Oct 2037not statedgate not printedScoping
7Coylton Farm300 MW582.4 MW30 Oct 2037not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20264182.4 MW
20271100 MW
20372600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Coylton 275kV Greener Grid ParkBattery storage450 MW30 Oct 2037Scoping
Coylton FarmBattery storage300 MW30 Oct 2037Awaiting Consents
Drongan Battery StorageBattery storage100 MW31 Oct 2027Scoping
McQuittiston FarmBattery storage29.9 MW29 May 2026Scoping
Hare Hill Extension Wind FarmOnshore wind29.75 MWnot statedBuilt
Mount FarmOnshore wind2.5 MW31 Oct 2026Consents Approved
Lessnessock Solar FarmSolar0 MW30 Jul 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.