N84 Grid

Creyke Beck 400kV Substation

NESO connection site, host NGET.

Contracted here8.15 GWNot yet connected, as printed
Entries in the queue10entries with a printed MW
Earliest connection date30 Jun 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,548.5 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Creyke Beck Battery 231 May 202430 Jun 202828.5 MW
Hornsea Power Station 431 May 202430 Oct 20281,500 MW
Hornsea Power Station 431 May 202431 Oct 20291,100 MW
CREYKE BECK31 May 202431 May 2033500 MW
Creyke Beck Solar Farm31 May 202431 May 2033320 MW
Hall Ings Farm Substation31 May 202430 Oct 2034100 MW
Creyke Beck PV & BESS Sub31 May 202430 May 2035249.9 MW
Bute Hydrogen Project 231 May 202430 Oct 20353,600 MW
KENLEY HOUSE SOLAR PARK22 Jul 202530 Oct 2039150 MW
Flinton Road22 Jul 202531 Oct 2039600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW5.0 GW10.0 GW2028: 1.5 GW2029: 2.6 GW2033: 3.4 GW2034: 3.5 GW2035: 7.4 GW2039: 8.1 GW2028203020322034203620398.1 GW
0 MW5.0 GW10.0 GW2028: 1.5 GW2029: 2.6 GW2033: 3.4 GW2034: 3.5 GW2035: 7.4 GW2039: 8.1 GW202820312034203720398.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20281,528.5 MW
20292,628.5 MW
20333,448.5 MW
20343,548.5 MW
20357,398.4 MW
20398,148.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Creyke Beck Battery 228.5 MW0 MW30 Jun 2028not statedgate not printedConsents Approved
2Hornsea Power Station 41,500 MW28.5 MW30 Oct 2028not statedgate not printedScoping
3Hornsea Power Station 41,100 MW1,528.5 MW31 Oct 2029not statedgate not printedScoping
4CREYKE BECK500 MW2,628.5 MW31 May 2033not statedgate not printedScoping
5Creyke Beck Solar Farm320 MW3,128.5 MW31 May 2033not statedgate not printedScoping
6Hall Ings Farm Substation100 MW3,448.5 MW30 Oct 2034not statedgate not printedScoping
7Creyke Beck PV & BESS Sub249.9 MW3,548.5 MW30 May 2035not statedgate not printedScoping
8Bute Hydrogen Project 23,600 MW3,798.4 MW30 Oct 20351gate 1Scoping
9KENLEY HOUSE SOLAR PARK150 MW7,398.4 MW30 Oct 2039not statedgate not printedScoping
10Flinton Road600 MW7,548.4 MW31 Oct 2039not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202821,528.5 MW
202911,100 MW
20332820 MW
20341100 MW
203523,849.9 MW
20392750 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bute Hydrogen Project 2Gas3,600 MW30 Oct 2035Scoping
Hornsea Power Station 4Offshore wind2,600 MW31 Oct 2029Scoping
Flinton RoadHybrid600 MW31 Oct 2039Scoping
CREYKE BECK (CLEAN AIR RENEWABLES LIMITED)Hybrid500 MW31 May 2033Scoping
Creyke Beck Solar FarmSolar320 MW31 May 2033Scoping
Creyke Beck PV & BESS SubHybrid249.9 MW30 May 2035Scoping
KENLEY HOUSE SOLAR PARKSolar150 MW30 Oct 2039Scoping
Hall Ings Farm SubstationSolar100 MW30 Oct 2034Scoping
Pillswood BESS Phase 1Battery storage49.9 MWnot statedBuilt
Pillswood BESS Phase 2Battery storage49.9 MWnot statedBuilt
Creyke Beck Battery 2Battery storage28.5 MW30 Jun 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.