N84 Grid

Crookston 132/33kV

NESO connection site, host SPT.

Contracted here0.03 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Dec 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue28 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Parkhouse 24MW BESS7 Nov 202528 Jun 202824 MW
Land at Nether Farm7 Nov 20251 Dec 20254 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2025: 4 MW2028: 28 MW202520262027202828 MW
0 MW20 MW40 MW2025: 4 MW2028: 28 MW202520262027202828 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20254 MW
202828 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Parkhouse 24MW BESS24 MW0 MW28 Jun 20282gate 2Consents Approved
2Land at Nether Farm4 MW24 MW1 Dec 2025not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202514 MW
2028124 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Parkhouse 24MW BESSBattery storage24 MW28 Jun 2028Consents Approved
Neilston Community Wind FarmOnshore wind10 MWnot statedBuilt
Land at Nether FarmOnshore wind4 MW1 Dec 2025Awaiting Consents
Carswell Hill Wind TurbineOnshore wind0.98 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.