N84 Grid

Currie 275/132kV

NESO connection site, host SPT.

Contracted here0.19 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date13 Apr 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue190 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Riccarton31 May 202413 Apr 2029150 MW
Kirknewton Solar and BESS7 Nov 202530 Apr 203040 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2029: 150 MW2030: 190 MW20292030190 MW
0 MW100 MW200 MW2029: 150 MW2030: 190 MW20292030190 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029150 MW
2030190 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Riccarton150 MW0 MW13 Apr 20291gate 1Scoping
2Kirknewton Solar and BESS40 MW150 MW30 Apr 2030not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291150 MW
2030140 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
RiccartonHybrid150 MW13 Apr 2029Scoping
Kirknewton Solar and BESSHybrid40 MW30 Apr 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.