The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Riccarton
31 May 2024 to 13 Apr 2029 (gate 1) - Kirknewton Solar and BESS
7 Nov 2025 to 30 Apr 2030 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Riccarton | 31 May 2024 | 13 Apr 2029 | 150 MW |
| Kirknewton Solar and BESS | 7 Nov 2025 | 30 Apr 2030 | 40 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 150 MW |
| 2030 | 190 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Riccarton | 150 MW | 0 MW | 13 Apr 2029 | 1 | gate 1 | Scoping |
| 2 | Kirknewton Solar and BESS | 40 MW | 150 MW | 30 Apr 2030 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 150 MW |
| 2030 | 1 | 40 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Riccarton | Hybrid | 150 MW | 13 Apr 2029 | Scoping |
| Kirknewton Solar and BESS | Hybrid | 40 MW | 30 Apr 2030 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.