Daines 400kV Substation

NESO connection site, host NGET.

Contracted here3.13 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date27 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,129.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Daines BESS31 May 202427 Oct 2028600 MW
Daines Green Energy Centre31 May 202431 Oct 2030480 MW
Carrington Lane BESS31 May 202430 Oct 20371,800 MW
Daines BESS31 May 202430 Nov 2037249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 600 MW2030: 1.1 GW2037: 3.1 GW2028203020322034203620373.1 GW
0 MW2.0 GW4.0 GW2028: 600 MW2030: 1.1 GW2037: 3.1 GW20282031203420373.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028600 MW
20301,080 MW
20373,129.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Daines BESS600 MW0 MW27 Oct 2028not statedgate not printedScoping
2Daines Green Energy Centre480 MW600 MW31 Oct 2030not statedgate not printedScoping
3Carrington Lane BESS1,800 MW1,080 MW30 Oct 20371gate 1Scoping
4Daines BESS249.9 MW2,880 MW30 Nov 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281600 MW
20301480 MW
203722,049.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Carrington Lane BESSBattery storage1,800 MW30 Oct 2037Scoping
Daines BESSBattery storage600 MW27 Oct 2028Scoping
Daines Green Energy CentreHybrid480 MW31 Oct 2030Scoping
Daines BESSBattery storage249.9 MW30 Nov 2037Scoping

Supported by National Energy SO Open Data