N84 Grid

Dalkeith 400kV Substation

NESO connection site, host SPT.

Contracted here0.60 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Jun 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue600 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Carberry BESS (was Smeaton BESS)31 May 202430 Jun 2031200 MW
Whitecraig BESS31 May 202430 Jun 2031200 MW
Salters Battery Storage27 Sep 202431 Oct 2031200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2031: 600 MW2031600 MW
0 MW400 MW800 MW2031: 600 MW2031600 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031600 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Carberry BESS (was Smeaton BESS)200 MW0 MW30 Jun 20311gate 1Scoping
2Whitecraig BESS200 MW200 MW30 Jun 20311gate 1Scoping
3Salters Battery Storage200 MW400 MW31 Oct 2031not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20313600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Carberry BESS (was Smeaton BESS)Battery storage200 MW30 Jun 2031Scoping
Salters Battery StorageBattery storage200 MW31 Oct 2031Awaiting Consents
Whitecraig BESSBattery storage200 MW30 Jun 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.