DALMARNOCK 132/33KV SUBSTATION

NESO connection site, host SPT.

Contracted here0.07 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date23 Feb 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue69 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dalmarnock Road BESS31 May 202423 Feb 202440 MW
Rutherglen Battery7 Nov 202531 Oct 202529 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2024: 40 MW2025: 69 MW2024202569 MW
0 MW40 MW80 MW2024: 40 MW2025: 69 MW2024202569 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202440 MW
202569 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dalmarnock Road BESS40 MW0 MW23 Feb 20242gate 2Under Construction/Commissioning
2Rutherglen Battery29 MW40 MW31 Oct 2025not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024140 MW
2025129 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Dalmarnock Road BESSBattery storage40 MW23 Feb 2024Under Construction/Commissioning
Rutherglen BatteryBattery storage29 MW31 Oct 2025Scoping

Supported by National Energy SO Open Data