N84 Grid

Derbyshire Connection Node A 400kV Substation

NESO connection site, host NGET.

Contracted here2.33 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Oct 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,332.4 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
West Haddon31 May 202430 Oct 20371,000 MW
Daventry High Impact Green Energy Hub (HIGEH) 131 May 202430 Oct 20371,000 MW
Park Farm Hybrid Solar and BESS31 May 202430 Oct 2037332.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2037: 2.3 GW20372.3 GW
0 MW1.3 GW2.5 GW2037: 2.3 GW20372.3 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20372,332.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1West Haddon1,000 MW0 MW30 Oct 20371gate 1Scoping
2Daventry High Impact Green Energy Hub (HIGEH) 11,000 MW1,000 MW30 Oct 20371gate 1Scoping
3Park Farm Hybrid Solar and BESS332.4 MW2,000 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203732,332.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Daventry High Impact Green Energy Hub (HIGEH) 1Hybrid1,000 MW30 Oct 2037Scoping
West HaddonSolar1,000 MW30 Oct 2037Scoping
Park Farm Hybrid Solar and BESSHybrid332.4 MW30 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.