N84 Grid

Devol Moor 132/33kV

NESO connection site, host SPT.

Contracted here0.52 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue518.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dougliehill BESS31 May 202431 Oct 202649 MW
Devol Moor Battery & Solar Project31 May 202427 Sep 2027400 MW
Langbank Solar and BESS31 May 202429 Oct 202749.9 MW
Devol Moor GSP7 Nov 202531 Oct 203120 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 49 MW2027: 499 MW2031: 519 MW202620272028202920302031519 MW
0 MW400 MW800 MW2026: 49 MW2027: 499 MW2031: 519 MW2026202820302031519 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202649 MW
2027498.9 MW
2031518.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dougliehill BESS49 MW0 MW31 Oct 20261gate 1Scoping
2Devol Moor Battery & Solar Project400 MW49 MW27 Sep 20271gate 1Scoping
3Langbank Solar and BESS49.9 MW449 MW29 Oct 2027not statedgate not printedScoping
4Devol Moor GSP20 MW498.9 MW31 Oct 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026149 MW
20272449.9 MW
2031120 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Devol Moor Battery & Solar ProjectBattery storage400 MW27 Sep 2027Scoping
Langbank Solar and BESSHybrid49.9 MW29 Oct 2027Scoping
Dougliehill BESSBattery storage49 MW31 Oct 2026Scoping
InverclydeOnshore wind24 MWnot statedBuilt
Devol Moor GSP (SP DISTRIBUTION PLC)Battery storage20 MW31 Oct 2031Scoping
Harelaw Gas GenerationGas20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.