N84 Grid

Devonside 132/33kV

NESO connection site, host SPT.

Contracted here0.21 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date18 Aug 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue209.5 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Devonside BESS31 May 202418 Aug 202849.5 MW
Bankhead 25MW BESS27 Sep 202430 Apr 203025 MW
Windburn Wind Farm22 Jul 202531 Oct 203475 MW
Longriggs Energy Park22 Jul 202530 Apr 203960 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2028: 50 MW2030: 75 MW2034: 150 MW2039: 210 MW202820302032203420362039210 MW
0 MW125 MW250 MW2028: 50 MW2030: 75 MW2034: 150 MW2039: 210 MW20282031203420372039210 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.5 MW
203074.5 MW
2034149.5 MW
2039209.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Devonside BESS49.5 MW0 MW18 Aug 2028not statedgate not printedScoping
2Bankhead 25MW BESS25 MW49.5 MW30 Apr 2030not statedgate not printedScoping
3Windburn Wind Farm75 MW74.5 MW31 Oct 20341gate 1Scoping
4Longriggs Energy Park60 MW149.5 MW30 Apr 2039not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.5 MW
2030125 MW
2034175 MW
2039160 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Windburn Wind FarmHybrid75 MW31 Oct 2034Scoping
Longriggs Energy ParkBattery storage60 MW30 Apr 2039Awaiting Consents
Devonside BESSBattery storage49.5 MW18 Aug 2028Scoping
Bankhead 25MW BESSBattery storage25 MW30 Apr 2030Scoping
Rhodders Wind FarmOnshore wind12.3 MWnot statedBuilt
Burnfoot EastOnshore wind10.8 MWnot statedBuilt
Overton FarmOnshore wind2.35 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.