N84 Grid

Dounreay GSP

NESO connection site, host SHET.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Apr 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue93.3 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bettyhill Phase 2 Wind Farm7 Nov 20251 Nov 202748 MW
Dounreay7 Nov 20251 Nov 202734 MW
Hill of Lybster Wind Generating Station7 Nov 202530 Apr 20231.5 MW
Forss BP Wind Turbine7 Nov 202531 Aug 20259.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2023: 2 MW2025: 11 MW2027: 93 MW2023202420252026202793 MW
0 MW50 MW100 MW2023: 2 MW2025: 11 MW2027: 93 MW20232025202793 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20231.5 MW
202511.3 MW
202793.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bettyhill Phase 2 Wind Farm48 MW0 MW1 Nov 20272gate 2Consents Approved
2Dounreay34 MW48 MW1 Nov 20272gate 2Scoping
3Hill of Lybster Wind Generating Station1.5 MW82 MW30 Apr 2023not statedgate not printedConsents Approved
4Forss BP Wind Turbine9.8 MW83.5 MW31 Aug 2025not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202311.5 MW
202519.8 MW
2027282 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Baillie Wind FarmOnshore wind52.5 MWnot statedBuilt
Bettyhill Phase 2 Wind FarmOnshore wind48 MW1 Nov 2027Consents Approved
Dounreay (Reay Power Limited)Battery storage34 MW1 Nov 2027Scoping
Forss BP Wind TurbineOnshore wind9.8 MW31 Aug 2025Scoping
Bettyhill Wind FarmOnshore wind5 MWnot statedBuilt
Hill of Lybster Wind Generating StationOnshore wind1.5 MW30 Apr 2023Consents Approved
Ackron Wind FarmOnshore wind0 MW31 Aug 2028Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.