N84 Grid

DOUNREAY 2 275 kV SUBSTATION

NESO connection site, host SHET.

Contracted here0.64 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Jun 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue643 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Forss Abbey Energy Storage7 Nov 202530 Jun 203149.9 MW
Crosskirk Energy Storage7 Nov 202530 Jun 203149.9 MW
Brae House Farm27 Sep 202431 Jul 2032500 MW
Melvich Wind Energy Hub (BEGA)22 Jul 202531 Oct 203343.2 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2031: 100 MW2032: 600 MW2033: 643 MW203120322033643 MW
0 MW400 MW800 MW2031: 100 MW2032: 600 MW2033: 643 MW203120322033643 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203199.8 MW
2032599.8 MW
2033643 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Forss Abbey Energy Storage49.9 MW0 MW30 Jun 2031not statedgate not printedScoping
2Crosskirk Energy Storage49.9 MW49.9 MW30 Jun 2031not statedgate not printedScoping
3Brae House Farm500 MW99.8 MW31 Jul 20321gate 1Scoping
4Melvich Wind Energy Hub (BEGA)43.2 MW599.8 MW31 Oct 20331gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2031299.8 MW
20321500 MW
2033143.2 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Brae House FarmBattery storage500 MW31 Jul 2032Scoping
Forss Abbey Energy StorageBattery storage49.9 MW30 Jun 2031Scoping
Crosskirk Energy StorageBattery storage49.9 MW30 Jun 2031Scoping
Melvich Wind Energy Hub (BEGA)Hybrid43.2 MW31 Oct 2033Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.