N84 Grid

Drumcross 132/33kV

NESO connection site, host SPT.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Jan 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue96.2 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Nairn Road Generation7 Nov 2025 to 31 Jan 2024, date already passed (gate not printed)
  • Nairn Road Bravo7 Nov 2025 to 31 Oct 2024, date already passed (gate not printed)
  • Drumcross ESS7 Nov 2025 to 31 Dec 2024, date already passed (gate not printed)
  • Camilty Wind Farm7 Nov 2025 to 30 Sep 2025, date already passed (gate not printed)
  • Drumcross GSP7 Nov 2025 to 30 Sep 2031 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Nairn Road Generation7 Nov 202531 Jan 202420 MW
Nairn Road Bravo7 Nov 202531 Oct 20244 MW
Drumcross ESS7 Nov 202531 Dec 202429.9 MW
Camilty Wind Farm7 Nov 202530 Sep 202521.6 MW
Drumcross GSP7 Nov 202530 Sep 203120.7 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2024: 54 MW2025: 76 MW2031: 96 MW2024202520262027202820292030203196 MW
0 MW50 MW100 MW2024: 54 MW2025: 76 MW2031: 96 MW202420262028203196 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202453.9 MW
202575.5 MW
203196.2 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Nairn Road Generation20 MW0 MW31 Jan 2024not statedgate not printedAwaiting Consents
2Nairn Road Bravo4 MW20 MW31 Oct 2024not statedgate not printedUnder Construction/Commissioning
3Drumcross ESS29.9 MW24 MW31 Dec 2024not statedgate not printedAwaiting Consents
4Camilty Wind Farm21.6 MW53.9 MW30 Sep 2025not statedgate not printedConsents Approved
5Drumcross GSP20.7 MW75.5 MW30 Sep 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024353.9 MW
2025121.6 MW
2031120.7 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Drumcross ESSBattery storage29.9 MW31 Dec 2024Awaiting Consents
Byers Brae Battery StorageBattery storage29.9 MWnot statedBuilt
West Benhar Wind FarmOnshore wind28.8 MWnot statedBuilt
Camilty Wind FarmOnshore wind21.6 MW30 Sep 2025Consents Approved
Drumcross GSP (SP DISTRIBUTION PLC)Onshore wind20.7 MW30 Sep 2031Scoping
Nairn Road GenerationGas20 MW31 Jan 2024Awaiting Consents
Nairn Road BravoGas8 MW31 Oct 2024Under Construction/Commissioning
Nairn Road AlphaGas4 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.