Dumfries 132/33kV

NESO connection site, host SPT.

Contracted here0.12 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date28 Apr 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue119.96 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Kellwood Road BESS31 May 202430 Jul 203040 MW
Annan Road BESS7 Nov 202528 Apr 202820 MW
Mosspark Energy Park21 Mar 202531 May 202950 MW
Locharmoss Solar & Battery7 Nov 202530 Oct 20369.96 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2028: 20 MW2029: 70 MW2030: 110 MW2036: 120 MW20282030203220342036120 MW
0 MW100 MW200 MW2028: 20 MW2029: 70 MW2030: 110 MW2036: 120 MW2028203120342036120 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202820 MW
202970 MW
2030110 MW
2036119.96 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Kellwood Road BESS40 MW0 MW30 Jul 20302gate 2Consents Approved
2Annan Road BESS20 MW40 MW28 Apr 2028not statedgate not printedScoping
3Mosspark Energy Park50 MW60 MW31 May 2029not statedgate not printedScoping
4Locharmoss Solar & Battery9.96 MW110 MW30 Oct 2036not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028120 MW
2029150 MW
2030140 MW
203619.96 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mosspark Energy ParkHybrid50 MW31 May 2029Scoping
Kellwood Road BESSBattery storage40 MW30 Jul 2030Consents Approved
DalswintonOnshore wind30 MWnot statedBuilt
Annan Road BESSBattery storage20 MW28 Apr 2028Scoping
Locharmoss Solar & BatteryHybrid9.96 MW30 Oct 2036Scoping
Dalswinton WindFarm ExtensionOnshore wind0 MW30 Sep 2029Scoping