Dungeness 400kV Substation

NESO connection site, host NGET.

Contracted here1.00 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Aug 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,000 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BLUE PLANET SOLAR31 May 202431 Aug 2031500 MW
Dungeness Energy Park31 May 202431 Oct 2037500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2031: 500 MW2037: 1.0 GW20312032203320342035203620371.0 GW
0 MW500 MW1.0 GW2031: 500 MW2037: 1.0 GW20312033203520371.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031500 MW
20371,000 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BLUE PLANET SOLAR500 MW0 MW31 Aug 2031not statedgate not printedScoping
2Dungeness Energy Park500 MW500 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311500 MW
20371500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Dungeness Energy ParkHybrid500 MW31 Oct 2037Scoping
BLUE PLANET SOLARHybrid500 MW31 Aug 2031Scoping
Dungeness BNuclear0 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.