Dunoon 132/33kV GSP Substation

NESO connection site, host SHET.

Contracted here0.05 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date25 Mar 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue45.48 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dunoon Energy Storage7 Nov 202530 Jun 202645 MW
Dunoon GSP (DNO)7 Nov 202525 Mar 20250.48 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2025: 0 MW2026: 45 MW2025202645 MW
0 MW25 MW50 MW2025: 0 MW2026: 45 MW2025202645 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.48 MW
202645.48 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dunoon Energy Storage45 MW0 MW30 Jun 20262gate 2Consents Approved
2Dunoon GSP (DNO)0.48 MW45 MW25 Mar 2025not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.48 MW
2026145 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Dunoon Energy StorageBattery storage45 MW30 Jun 2026Consents Approved
Dunoon GSP (DNO)Battery storage0.48 MW25 Mar 2025Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.