The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Dunoon Energy Storage
7 Nov 2025 to 30 Jun 2026, date already passed (gate 2) - Dunoon GSP (DNO)
7 Nov 2025 to 25 Mar 2025, date already passed (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Dunoon Energy Storage | 7 Nov 2025 | 30 Jun 2026 | 45 MW |
| Dunoon GSP (DNO) | 7 Nov 2025 | 25 Mar 2025 | 0.48 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 0.48 MW |
| 2026 | 45.48 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Dunoon Energy Storage | 45 MW | 0 MW | 30 Jun 2026 | 2 | gate 2 | Consents Approved |
| 2 | Dunoon GSP (DNO) | 0.48 MW | 45 MW | 25 Mar 2025 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 0.48 MW |
| 2026 | 1 | 45 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Dunoon Energy Storage | Battery storage | 45 MW | 30 Jun 2026 | Consents Approved |
| Dunoon GSP (DNO) | Battery storage | 0.48 MW | 25 Mar 2025 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.