N84 Grid

Dyce 132/33kV GSP

NESO connection site, host SHET.

Contracted here0.28 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date30 Apr 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue228.42 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Kincraig Energy Centre31 May 202430 Apr 202520.62 MW
Dyce Energy Storage Facility7 Nov 202531 Mar 202630 MW
Perwinnes31 May 202431 Oct 202845 MW
Dyce Battery Storage7 Nov 202531 Oct 202849.9 MW
Goval BESS7 Nov 202530 Jun 202633 MW
Lochgreens BESS7 Nov 202531 Jul 202849.9 MW
Middleton of Potterton Farm7 Nov 202531 Mar 202949.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 21 MW2026: 84 MW2028: 228 MW2029: 278 MW20252026202720282029278 MW
0 MW200 MW400 MW2025: 21 MW2026: 84 MW2028: 228 MW2029: 278 MW202520272029278 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202520.62 MW
202683.62 MW
2028228.42 MW
2029278.32 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Kincraig Energy Centre20.62 MW0 MW30 Apr 20252gate 2Under Construction/Commissioning
2Dyce Energy Storage Facility30 MW20.62 MW31 Mar 20262gate 2Scoping
3Perwinnes45 MW50.62 MW31 Oct 20282gate 2Consents Approved
4Dyce Battery Storage49.9 MW95.62 MW31 Oct 20282gate 2Consents Approved
5Goval BESS33 MW145.52 MW30 Jun 20261gate 1Scoping
6Lochgreens BESS49.9 MW178.52 MW31 Jul 20281gate 1Scoping
7Middleton of Potterton Farm49.9 MW228.42 MW31 Mar 20291gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025120.62 MW
2026263 MW
20283144.8 MW
2029149.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Middleton of Potterton FarmBattery storage49.9 MW31 Mar 2029Scoping
Lochgreens BESSBattery storage49.9 MW31 Jul 2028Scoping
Dyce Battery StorageBattery storage49.9 MW31 Oct 2028Consents Approved
PerwinnesHybrid45 MW31 Oct 2028Consents Approved
Goval BESSBattery storage33 MW30 Jun 2026Scoping
Dyce Energy Storage FacilityBattery storage30 MW31 Mar 2026Scoping
Kincraig Energy CentreHybrid20.62 MW30 Apr 2025Under Construction/Commissioning
Stoneywood Mills (Wiggins Teape Stoneywood)Gas12 MWnot statedBuilt
AECC (Rowett)Biomass and waste4 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.