N84 Grid

Earba PSH Powerhouse Substation

NESO connection site, host SHET.

Contracted here1.80 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Dec 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,800 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Earba PSH31 May 2024 to 31 Dec 2032 (gate not printed)
  • Earba PSH31 May 2024 to 31 Oct 2035 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Earba PSH31 May 202431 Dec 2032600 MW
Earba PSH31 May 202431 Oct 20351,200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2032: 600 MW2035: 1.8 GW20322033203420351.8 GW
0 MW1.0 GW2.0 GW2032: 600 MW2035: 1.8 GW20322033203420351.8 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2032600 MW
20351,800 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Earba PSH600 MW0 MW31 Dec 2032not statedgate not printedConsents Approved
2Earba PSH1,200 MW600 MW31 Oct 2035not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20321600 MW
203511,200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Earba PSHHydro and pumped storage1,800 MW31 Oct 2035Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.