Earl Shilton 400kV Substation

NESO connection site, host NGET.

Contracted here1.65 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date26 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,649.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Earl Shilton BESS31 May 202426 Oct 2029500 MW
Enderby BESS31 May 202430 Nov 2033249.9 MW
Enderby Farm31 May 202431 Oct 2034200 MW
Enderby Farm 231 May 202431 Oct 2034700 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2029: 500 MW2033: 750 MW2034: 1.6 GW2029203020312032203320341.6 GW
0 MW1.0 GW2.0 GW2029: 500 MW2033: 750 MW2034: 1.6 GW20292031203320341.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029500 MW
2033749.9 MW
20341,649.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Earl Shilton BESS500 MW0 MW26 Oct 2029not statedgate not printedScoping
2Enderby BESS249.9 MW500 MW30 Nov 20331gate 1Scoping
3Enderby Farm200 MW749.9 MW31 Oct 20341gate 1Scoping
4Enderby Farm 2700 MW949.9 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291500 MW
20331249.9 MW
20342900 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Enderby Farm 2Hybrid700 MW31 Oct 2034Scoping
Earl Shilton BESSBattery storage500 MW26 Oct 2029Scoping
Enderby BESSBattery storage249.9 MW30 Nov 2033Scoping
Enderby FarmHybrid200 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.