The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- East Anglia Three
31 May 2024 to 31 Jan 2026, date already passed (gate not printed) - East Anglia Three
31 May 2024 to 31 Dec 2028 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| East Anglia Three | 31 May 2024 | 31 Jan 2026 | 1,200 MW |
| East Anglia Three | 31 May 2024 | 31 Dec 2028 | 100 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 1,200 MW |
| 2028 | 1,300 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | East Anglia Three | 1,200 MW | 0 MW | 31 Jan 2026 | not stated | gate not printed | Consents Approved |
| 2 | East Anglia Three | 100 MW | 1,200 MW | 31 Dec 2028 | not stated | gate not printed | Consents Approved |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 1,200 MW |
| 2028 | 1 | 100 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| East Anglia Three | Offshore wind | 1,300 MW | 31 Dec 2028 | Consents Approved |
Supported by National Energy SO Open Data