East Claydon 400kV Substation

NESO connection site, host NGET.

Contracted here5.15 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date1 Oct 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4,125 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
East Claydon Storage31 May 20241 Oct 2026500 MW
Rosefield31 May 202431 Oct 2031500 MW
East Claydon Green Energy Centre31 May 20241 Oct 20341,025 MW
East Claydon Greener Grid Park31 May 202430 Nov 2034650 MW
East Claydon High Impact Green Energy Hub (HIGEH) 131 May 20246 Dec 20361,000 MW
Alderton PV & BESS Station31 May 202431 Oct 2037450 MW
East Claydon Green Energy Centre31 May 202431 Oct 20381,025 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2026: 500 MW2031: 1.0 GW2034: 2.7 GW2036: 3.7 GW2037: 4.1 GW2038: 5.2 GW20262028203020322034203620385.2 GW
0 MW4.0 GW8.0 GW2026: 500 MW2031: 1.0 GW2034: 2.7 GW2036: 3.7 GW2037: 4.1 GW2038: 5.2 GW20262030203420385.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026500 MW
20311,000 MW
20342,675 MW
20363,675 MW
20374,125 MW
20385,150 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1East Claydon Storage500 MW0 MW1 Oct 20261gate 1Scoping
2Rosefield500 MW500 MW31 Oct 2031not statedgate not printedAwaiting Consents
3East Claydon Green Energy Centre1,025 MW1,000 MW1 Oct 2034not statedgate not printedAwaiting Consents
4East Claydon Greener Grid Park650 MW2,025 MW30 Nov 20341gate 1Scoping
5East Claydon High Impact Green Energy Hub (HIGEH) 11,000 MW2,675 MW6 Dec 20361gate 1Scoping
6Alderton PV & BESS Station450 MW3,675 MW31 Oct 20371gate 1Scoping
7East Claydon Green Energy Centre1,025 MW4,125 MW31 Oct 2038not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20261500 MW
20311500 MW
203421,675 MW
203611,000 MW
20371450 MW
203811,025 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
East Claydon Green Energy CentreHybrid2,050 MW31 Oct 2038Awaiting Consents
East Claydon High Impact Green Energy Hub (HIGEH) 1Hybrid1,000 MW6 Dec 2036Scoping
East Claydon Greener Grid ParkBattery storage650 MW30 Nov 2034Scoping
East Claydon StorageBattery storage500 MW1 Oct 2026Scoping
RosefieldHybrid500 MW31 Oct 2031Awaiting Consents
Alderton PV & BESS StationHybrid450 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data