N84 Grid

East Kent connection node A 400kV Substation

NESO connection site, host NGET.

Contracted here3.52 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,520 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sellindge West31 May 202431 Oct 20331,000 MW
Dungeness Energy Park (Dungeness 400kV)27 Sep 202431 Oct 2033500 MW
GF SELLINDGE BESS20 Dec 202431 Oct 2036300 MW
Henley Downs Farm BESS22 Jul 202531 Oct 2037240 MW
Lightsource Newchurch PV/BESS31 May 202431 Oct 2037240 MW
Fairmead and Yewtree Farm31 May 202431 Oct 2037240 MW
Newchurch High Impact Energy Hub22 Jul 202531 Oct 20371,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2033: 1.5 GW2036: 1.8 GW2037: 3.5 GW203320342035203620373.5 GW
0 MW2.0 GW4.0 GW2033: 1.5 GW2036: 1.8 GW2037: 3.5 GW2033203520373.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20331,500 MW
20361,800 MW
20373,520 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sellindge West1,000 MW0 MW31 Oct 20331gate 1Scoping
2Dungeness Energy Park (Dungeness 400kV)500 MW1,000 MW31 Oct 2033not statedgate not printedScoping
3GF SELLINDGE BESS300 MW1,500 MW31 Oct 20361gate 1Scoping
4Henley Downs Farm BESS240 MW1,800 MW31 Oct 20371gate 1Scoping
5Lightsource Newchurch PV/BESS240 MW2,040 MW31 Oct 2037not statedgate not printedScoping
6Fairmead and Yewtree Farm240 MW2,280 MW31 Oct 20371gate 1Scoping
7Newchurch High Impact Energy Hub1,000 MW2,520 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203321,500 MW
20361300 MW
203741,720 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Newchurch High Impact Energy HubHybrid1,000 MW31 Oct 2037Scoping
Sellindge WestHybrid1,000 MW31 Oct 2033Scoping
Dungeness Energy Park (Dungeness 400kV)Hybrid500 MW31 Oct 2033Scoping
GF SELLINDGE BESSBattery storage300 MW31 Oct 2036Scoping
Lightsource Newchurch PV/BESSHybrid240 MW31 Oct 2037Scoping
Fairmead and Yewtree FarmBattery storage240 MW31 Oct 2037Scoping
Henley Downs Farm BESSBattery storage240 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.