The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Canterbury North
31 May 2024 to 31 Oct 2030 (gate 1) - Project Cobalt
5 Nov 2024 to 30 Oct 2036 (gate 1) - Project Invicta
20 Dec 2024 to 31 Oct 2036 (gate 1) - Woodlands Farm BESS
21 Mar 2025 to 31 Oct 2036 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Canterbury North | 31 May 2024 | 31 Oct 2030 | 1,000 MW |
| Project Cobalt | 5 Nov 2024 | 30 Oct 2036 | 1,000 MW |
| Project Invicta | 20 Dec 2024 | 31 Oct 2036 | 350 MW |
| Woodlands Farm BESS | 21 Mar 2025 | 31 Oct 2036 | 227.5 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2030 | 1,000 MW |
| 2036 | 2,577.5 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Canterbury North | 1,000 MW | 0 MW | 31 Oct 2030 | 1 | gate 1 | Scoping |
| 2 | Project Cobalt | 1,000 MW | 1,000 MW | 30 Oct 2036 | 1 | gate 1 | Scoping |
| 3 | Project Invicta | 350 MW | 2,000 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
| 4 | Woodlands Farm BESS | 227.5 MW | 2,350 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2030 | 1 | 1,000 MW |
| 2036 | 3 | 1,577.5 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Canterbury North | Hybrid | 1,000 MW | 31 Oct 2030 | Scoping |
| Project Cobalt | Interconnector | 1,000 MW | 30 Oct 2036 | Scoping |
| Project Invicta | Hybrid | 350 MW | 31 Oct 2036 | Scoping |
| Woodlands Farm BESS | Battery storage | 227.5 MW | 31 Oct 2036 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.