East Kent Connection Node B 400kV Substation

NESO connection site, host NGET.

Contracted here2.58 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,577.5 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Canterbury North31 May 202431 Oct 20301,000 MW
Project Cobalt5 Nov 202430 Oct 20361,000 MW
Project Invicta20 Dec 202431 Oct 2036350 MW
Woodlands Farm BESS21 Mar 202531 Oct 2036227.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2030: 1.0 GW2036: 2.6 GW20302031203220332034203520362.6 GW
0 MW2.0 GW4.0 GW2030: 1.0 GW2036: 2.6 GW20302032203420362.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20301,000 MW
20362,577.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Canterbury North1,000 MW0 MW31 Oct 20301gate 1Scoping
2Project Cobalt1,000 MW1,000 MW30 Oct 20361gate 1Scoping
3Project Invicta350 MW2,000 MW31 Oct 20361gate 1Scoping
4Woodlands Farm BESS227.5 MW2,350 MW31 Oct 20361gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203011,000 MW
203631,577.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Canterbury NorthHybrid1,000 MW31 Oct 2030Scoping
Project CobaltInterconnector1,000 MW30 Oct 2036Scoping
Project InvictaHybrid350 MW31 Oct 2036Scoping
Woodlands Farm BESSBattery storage227.5 MW31 Oct 2036Scoping