The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Cathkin Energy Storage
7 Nov 2025 to 31 Jul 2024, date already passed (gate 2) - Rogerton Cottage BESS
31 May 2024 to 26 Mar 2027 (gate 2) - Rutherend Farm
27 Sep 2024 to 31 Oct 2033 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Cathkin Energy Storage | 7 Nov 2025 | 31 Jul 2024 | 49.9 MW |
| Rogerton Cottage BESS | 31 May 2024 | 26 Mar 2027 | 55 MW |
| Rutherend Farm | 27 Sep 2024 | 31 Oct 2033 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 49.9 MW |
| 2027 | 104.9 MW |
| 2033 | 304.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Cathkin Energy Storage | 49.9 MW | 0 MW | 31 Jul 2024 | 2 | gate 2 | Scoping |
| 2 | Rogerton Cottage BESS | 55 MW | 49.9 MW | 26 Mar 2027 | 2 | gate 2 | Scoping |
| 3 | Rutherend Farm | 200 MW | 104.9 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 49.9 MW |
| 2027 | 1 | 55 MW |
| 2033 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Rutherend Farm | Battery storage | 200 MW | 31 Oct 2033 | Scoping |
| Rogerton Cottage BESS | Battery storage | 55 MW | 26 Mar 2027 | Scoping |
| Cathkin Energy Storage | Battery storage | 49.9 MW | 31 Jul 2024 | Scoping |
| Calderwater | Onshore wind | 39 MW | not stated | Built |
| Cathkin Quarry BESS | Battery storage | 0 MW | 6 Jul 2026 | Scoping |