N84 Grid

East Kilbride 275/33kV GSP

NESO connection site, host SPT.

Contracted here0.30 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Jul 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue304.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cathkin Energy Storage7 Nov 202531 Jul 202449.9 MW
Rogerton Cottage BESS31 May 202426 Mar 202755 MW
Rutherend Farm27 Sep 202431 Oct 2033200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2024: 50 MW2027: 105 MW2033: 305 MW202420262028203020322033305 MW
0 MW200 MW400 MW2024: 50 MW2027: 105 MW2033: 305 MW2024202720302033305 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202449.9 MW
2027104.9 MW
2033304.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cathkin Energy Storage49.9 MW0 MW31 Jul 20242gate 2Scoping
2Rogerton Cottage BESS55 MW49.9 MW26 Mar 20272gate 2Scoping
3Rutherend Farm200 MW104.9 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024149.9 MW
2027155 MW
20331200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Rutherend FarmBattery storage200 MW31 Oct 2033Scoping
Rogerton Cottage BESSBattery storage55 MW26 Mar 2027Scoping
Cathkin Energy StorageBattery storage49.9 MW31 Jul 2024Scoping
CalderwaterOnshore wind39 MWnot statedBuilt
Cathkin Quarry BESSBattery storage0 MW6 Jul 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.