East Kilbride South 275/33kV

NESO connection site, host SPT.

Contracted here0.24 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Mar 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue230 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rigmuir Windfarm7 Nov 202531 Mar 202413.5 MW
Langlands Gate7 Nov 202531 Aug 202716.5 MW
Dunns Farm7 Nov 202529 Oct 202722.8 MW
Langlands Business Park7 Nov 202530 Oct 202720 MW
Mossmulloch Wind Farm7 Nov 202531 Oct 202843.2 MW
Strathaven West7 Nov 202523 Jul 2029114 MW
East Kilbride South GSP7 Nov 202531 Oct 203313.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2024: 14 MW2027: 73 MW2028: 116 MW2029: 230 MW2033: 243 MW202420262028203020322033243 MW
0 MW125 MW250 MW2024: 14 MW2027: 73 MW2028: 116 MW2029: 230 MW2033: 243 MW2024202720302033243 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202413.5 MW
202772.8 MW
2028116 MW
2029230 MW
2033243.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rigmuir Windfarm13.5 MW0 MW31 Mar 2024not statedgate not printedScoping
2Langlands Gate16.5 MW13.5 MW31 Aug 2027not statedgate not printedScoping
3Dunns Farm22.8 MW30 MW29 Oct 2027not statedgate not printedScoping
4Langlands Business Park20 MW52.8 MW30 Oct 2027not statedgate not printedScoping
5Mossmulloch Wind Farm43.2 MW72.8 MW31 Oct 2028not statedgate not printedScoping
6Strathaven West114 MW116 MW23 Jul 2029not statedgate not printedScoping
7East Kilbride South GSP13.4 MW230 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024113.5 MW
2027359.3 MW
2028143.2 MW
20291114 MW
2033113.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Strathaven WestOnshore wind114 MW23 Jul 2029Scoping
Mossmulloch Wind FarmOnshore wind43.2 MW31 Oct 2028Scoping
Dunns FarmBattery storage22.8 MW29 Oct 2027Scoping
Langlands Business ParkBattery storage20 MW30 Oct 2027Scoping
Langlands GateBattery storage16.5 MW31 Aug 2027Scoping
Rigmuir WindfarmOnshore wind13.5 MW31 Mar 2024Scoping
East Kilbride South GSP (SP DISTRIBUTION PLC)Onshore wind13.4 MW31 Oct 2033Scoping
Ardoch and Over Enoch Wind FarmOnshore wind11.5 MWnot statedBuilt