Eaton Socon 400kV Substation

NESO connection site, host NGET.

Contracted here1.55 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,549.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Eaton Socon Solar31 May 202431 Oct 2028500 MW
Eaton Socon PV Storage31 May 202430 Oct 202949.9 MW
Eaton Socon High Impact Green Energy Hub (HIGEH) 131 May 202430 Oct 20331,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 500 MW2029: 550 MW2033: 1.5 GW2028202920302031203220331.5 GW
0 MW1.0 GW2.0 GW2028: 500 MW2029: 550 MW2033: 1.5 GW20282030203220331.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028500 MW
2029549.9 MW
20331,549.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Eaton Socon Solar500 MW0 MW31 Oct 2028not statedgate not printedScoping
2Eaton Socon PV Storage49.9 MW500 MW30 Oct 2029not statedgate not printedScoping
3Eaton Socon High Impact Green Energy Hub (HIGEH) 11,000 MW549.9 MW30 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281500 MW
2029149.9 MW
203311,000 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Eaton Socon High Impact Green Energy Hub (HIGEH) 1Hybrid1,000 MW30 Oct 2033Scoping
Little BarfordHybrid740 MWnot statedBuilt
Eaton Socon SolarHybrid500 MW31 Oct 2028Scoping
Eaton Socon PV StorageHybrid49.9 MW30 Oct 2029Scoping
One Planet Solar FarmSolar0 MW31 Oct 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.