Eccles 400/132kV

NESO connection site, host SPT.

Contracted here1.40 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date12 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,359.1 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Eccles BESS31 May 202412 Apr 2026500 MW
Zenobe Eccles Battery Storage31 May 202430 Apr 2026400 MW
AMP Eccles BESS31 May 202431 Oct 202949.9 MW
Eccles GSP7 Nov 202530 Sep 203019.2 MW
Pittlesheugh Farm31 May 202431 Oct 2030340 MW
Coldstream BESS27 Sep 202431 Oct 203050 MW
Coldstream Solar PV Plant22 Jul 202531 Jul 203140.56 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 900 MW2029: 950 MW2030: 1.4 GW2031: 1.4 GW2026202720282029203020311.4 GW
0 MW1.0 GW2.0 GW2026: 900 MW2029: 950 MW2030: 1.4 GW2031: 1.4 GW20262028203020311.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026900 MW
2029949.9 MW
20301,359.1 MW
20311,399.66 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Eccles BESS500 MW0 MW12 Apr 20262gate 2Under Construction/Commissioning
2Zenobe Eccles Battery Storage400 MW500 MW30 Apr 20262gate 2Under Construction/Commissioning
3AMP Eccles BESS49.9 MW900 MW31 Oct 2029not statedgate not printedScoping
4Eccles GSP19.2 MW949.9 MW30 Sep 2030not statedgate not printedScoping
5Pittlesheugh Farm340 MW969.1 MW31 Oct 20301gate 1Scoping
6Coldstream BESS50 MW1,309.1 MW31 Oct 20301gate 1Scoping
7Coldstream Solar PV Plant40.56 MW1,359.1 MW31 Jul 20311gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262900 MW
2029149.9 MW
20303409.2 MW
2031140.56 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Eccles BESSBattery storage500 MW12 Apr 2026Under Construction/Commissioning
Zenobe Eccles Battery StorageBattery storage400 MW30 Apr 2026Under Construction/Commissioning
Pittlesheugh FarmBattery storage340 MW31 Oct 2030Scoping
Coldstream BESSBattery storage50 MW31 Oct 2030Scoping
AMP Eccles BESSBattery storage49.9 MW31 Oct 2029Scoping
Coldstream Solar PV PlantSolar40.56 MW31 Jul 2031Scoping
Eccles GSP (SP DISTRIBUTION PLC)Solar19.2 MW30 Sep 2030Scoping