N84 Grid

Eday 132/33kV GSP Substation

NESO connection site, host SHET.

Contracted here0.08 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 May 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue77.8 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Orkney Community Wind Farm - Faray7 Nov 202530 May 203030 MW
Fall of Warness7 Nov 202530 May 203022.8 MW
Greentoft Farm7 Nov 202531 Oct 203325 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2030: 53 MW2033: 78 MW203020312032203378 MW
0 MW40 MW80 MW2030: 53 MW2033: 78 MW203020312032203378 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203052.8 MW
203377.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Orkney Community Wind Farm - Faray30 MW0 MW30 May 2030not statedgate not printedScoping
2Fall of Warness22.8 MW30 MW30 May 2030not statedgate not printedScoping
3Greentoft Farm25 MW52.8 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2030252.8 MW
2033125 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Orkney Community Wind Farm - FarayOnshore wind30 MW30 May 2030Scoping
Greentoft FarmOnshore wind25 MW31 Oct 2033Scoping
Fall of WarnessTidal and wave22.8 MW30 May 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.