N84 Grid

Edinbane GSP

NESO connection site, host SHET.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date16 Apr 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue197 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ben Sca7 Nov 202516 Apr 202840.8 MW
Balmeanach Wind Farm7 Nov 202530 Nov 202945 MW
Beinn Mheadhonach7 Nov 202530 Nov 202923 MW
Edinbane Windfarm31 May 202430 Apr 203348.6 MW
Glenmore21 Mar 202531 Oct 203439.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2028: 41 MW2029: 109 MW2033: 157 MW2034: 197 MW2028202920302031203220332034197 MW
0 MW100 MW200 MW2028: 41 MW2029: 109 MW2033: 157 MW2034: 197 MW2028203020322034197 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202840.8 MW
2029108.8 MW
2033157.4 MW
2034197 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ben Sca40.8 MW0 MW16 Apr 2028not statedgate not printedConsents Approved
2Balmeanach Wind Farm45 MW40.8 MW30 Nov 2029not statedgate not printedScoping
3Beinn Mheadhonach23 MW85.8 MW30 Nov 2029not statedgate not printedConsents Approved
4Edinbane Windfarm48.6 MW108.8 MW30 Apr 20331gate 1Scoping
5Glenmore39.6 MW157.4 MW31 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028140.8 MW
2029268 MW
2033148.6 MW
2034139.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Edinbane WindfarmHybrid90 MW30 Apr 2033Scoping
Balmeanach Wind FarmOnshore wind45 MW30 Nov 2029Scoping
Ben ScaOnshore wind40.8 MW16 Apr 2028Consents Approved
GlenmoreOnshore wind39.6 MW31 Oct 2034Scoping
Beinn MheadhonachOnshore wind23 MW30 Nov 2029Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.