Eggborough 400kV Substation

NESO connection site, host NGET.

Contracted here3.00 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date1 Oct 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue3,000 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Eggborough CCGT - OCGT - BESS31 May 20241 Oct 20261,999 MW
Eggborough CCGT - OCGT - BESS31 May 20241 Oct 2027451 MW
Eggborough31 May 202416 Jun 2032550 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2026: 2.0 GW2027: 2.5 GW2032: 3.0 GW20262027202820292030203120323.0 GW
0 MW2.0 GW4.0 GW2026: 2.0 GW2027: 2.5 GW2032: 3.0 GW20262028203020323.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20261,999 MW
20272,450 MW
20323,000 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Eggborough CCGT - OCGT - BESS1,999 MW0 MW1 Oct 2026not statedgate not printedAwaiting Consents
2Eggborough CCGT - OCGT - BESS451 MW1,999 MW1 Oct 2027not statedgate not printedAwaiting Consents
3Eggborough550 MW2,450 MW16 Jun 2032not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202611,999 MW
20271451 MW
20321550 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Eggborough CCGT and BESSHybrid2,450 MW1 Oct 2027Awaiting Consents
Eggborough (SSE EGGBOROUGH LIMITED)Battery storage550 MW16 Jun 2032Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.