Elderslie 132/33kV

NESO connection site, host SPT.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date28 Jun 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue88.6 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Well Street Paisley31 May 202428 Jun 202849.9 MW
Middleton Farm Solar31 May 202428 Jun 202838.7 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2028: 89 MW202889 MW
0 MW50 MW100 MW2028: 89 MW202889 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202888.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Well Street Paisley49.9 MW0 MW28 Jun 20282gate 2Consents Approved
2Middleton Farm Solar38.7 MW49.9 MW28 Jun 2028not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028288.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Well Street PaisleyBattery storage49.9 MW28 Jun 2028Consents Approved
Middleton Farm SolarSolar38.7 MW28 Jun 2028Scoping

Supported by National Energy SO Open Data