The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Speyslaw Solar
7 Nov 2025 to 30 Jun 2025, date already passed (gate not printed) - Milltown Airfield Solar Farm
7 Nov 2025 to 28 Feb 2027 (gate not printed) - Speyslaw (Duplication with Project #PRO-001278)
7 Nov 2025 to 1 Jul 2027 (gate not printed) - Elgin BESS
31 May 2024 to 31 Oct 2028 (gate not printed) - Loanhead Farm BESS
7 Nov 2025 to 31 Oct 2030 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Speyslaw Solar | 7 Nov 2025 | 30 Jun 2025 | 20 MW |
| Milltown Airfield Solar Farm | 7 Nov 2025 | 28 Feb 2027 | 49.9 MW |
| Speyslaw (Duplication with Project #PRO-001278) | 7 Nov 2025 | 1 Jul 2027 | 20 MW |
| Elgin BESS | 31 May 2024 | 31 Oct 2028 | 30 MW |
| Loanhead Farm BESS | 7 Nov 2025 | 31 Oct 2030 | 50 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 20 MW |
| 2027 | 89.9 MW |
| 2028 | 119.9 MW |
| 2030 | 169.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Speyslaw Solar | 20 MW | 0 MW | 30 Jun 2025 | not stated | gate not printed | Consents Approved |
| 2 | Milltown Airfield Solar Farm | 49.9 MW | 20 MW | 28 Feb 2027 | not stated | gate not printed | Scoping |
| 3 | Speyslaw (Duplication with Project #PRO-001278) | 20 MW | 69.9 MW | 1 Jul 2027 | not stated | gate not printed | Scoping |
| 4 | Elgin BESS | 30 MW | 89.9 MW | 31 Oct 2028 | not stated | gate not printed | Scoping |
| 5 | Loanhead Farm BESS | 50 MW | 119.9 MW | 31 Oct 2030 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 20 MW |
| 2027 | 2 | 69.9 MW |
| 2028 | 1 | 30 MW |
| 2030 | 1 | 50 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Loanhead Farm BESS | Battery storage | 50 MW | 31 Oct 2030 | Scoping |
| Milltown Airfield Solar Farm | Solar | 49.9 MW | 28 Feb 2027 | Scoping |
| Elgin BESS | Battery storage | 30 MW | 31 Oct 2028 | Scoping |
| Speyslaw Solar | Solar | 20 MW | 30 Jun 2025 | Consents Approved |
| Speyslaw (Duplication with Project #PRO-001278) | Hybrid | 20 MW | 1 Jul 2027 | Scoping |