N84 Grid

Feckenham 400kV Substation

NESO connection site, host NGET.

Contracted here3.48 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,575 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Feckenham Greener Grid Park31 May 202431 Oct 202812 MW
Feckenham31 May 202421 Jul 2029500 MW
Feckenham Green Energy Centre31 May 202430 Oct 20321,025 MW
Feckenham Greener Grid Park31 May 202431 Oct 2032138 MW
Boom Power Feckenham Generation Hub31 May 202431 Oct 2033400 MW
Feckenham Energy Park31 May 202431 Oct 2033500 MW
Feckenham31 May 202431 Oct 2036400 MW
Feckenham PV & BESS Station27 Sep 202430 Oct 2037400 MW
Feckenham 100MW BESS22 Jul 202530 Oct 2037100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 12 MW2029: 512 MW2032: 1.7 GW2033: 2.6 GW2036: 3.0 GW2037: 3.5 GW2028203020322034203620373.5 GW
0 MW2.0 GW4.0 GW2028: 12 MW2029: 512 MW2032: 1.7 GW2033: 2.6 GW2036: 3.0 GW2037: 3.5 GW20282031203420373.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202812 MW
2029512 MW
20321,675 MW
20332,575 MW
20362,975 MW
20373,475 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Feckenham Greener Grid Park12 MW0 MW31 Oct 20281gate 1Scoping
2Feckenham500 MW12 MW21 Jul 2029not statedgate not printedScoping
3Feckenham Green Energy Centre1,025 MW512 MW30 Oct 2032not statedgate not printedScoping
4Feckenham Greener Grid Park138 MW1,537 MW31 Oct 20321gate 1Scoping
5Boom Power Feckenham Generation Hub400 MW1,675 MW31 Oct 20331gate 1Scoping
6Feckenham Energy Park500 MW2,075 MW31 Oct 2033not statedgate not printedScoping
7Feckenham400 MW2,575 MW31 Oct 20361gate 1Awaiting Consents
8Feckenham PV & BESS Station400 MW2,975 MW30 Oct 20371gate 1Scoping
9Feckenham 100MW BESS100 MW3,375 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028112 MW
20291500 MW
203221,163 MW
20332900 MW
20361400 MW
20372500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Feckenham Green Energy CentreHybrid1,025 MW30 Oct 2032Scoping
Feckenham (IGP SOLAR 14 LIMITED)Hybrid500 MW21 Jul 2029Scoping
Feckenham Energy ParkBattery storage500 MW31 Oct 2033Scoping
Boom Power Feckenham Generation HubHybrid400 MW31 Oct 2033Scoping
Feckenham PV & BESS StationHybrid400 MW30 Oct 2037Scoping
Feckenham (ENSO GREEN HOLDINGS X LIMITED)Hybrid400 MW31 Oct 2036Awaiting Consents
Feckenham Greener Grid ParkBattery storage150 MW31 Oct 2032Scoping
Feckenham 100MW BESSBattery storage100 MW30 Oct 2037Scoping
RedditchGas29 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.