Ferrybridge C 275kV Substation

NESO connection site, host NGET.

Contracted here1.67 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date4 Oct 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,669.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ferrybridge D31 May 20244 Oct 20301,220 MW
Ferrybridge D31 May 20241 Jun 2034200 MW
Ferrybridge C PV & BESS Substation31 May 202424 Oct 2035249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2030: 1.2 GW2034: 1.4 GW2035: 1.7 GW2030203120322033203420351.7 GW
0 MW1.0 GW2.0 GW2030: 1.2 GW2034: 1.4 GW2035: 1.7 GW20302032203420351.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20301,220 MW
20341,420 MW
20351,669.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ferrybridge D1,220 MW0 MW4 Oct 2030not statedgate not printedScoping
2Ferrybridge D200 MW1,220 MW1 Jun 2034not statedgate not printedAwaiting Consents
3Ferrybridge C PV & BESS Substation249.9 MW1,420 MW24 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203011,220 MW
20341200 MW
20351249.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Ferrybridge DHybrid1,420 MW1 Jun 2034Awaiting Consents
Ferrybridge C PV & BESS SubstationHybrid249.9 MW24 Oct 2035Scoping