N84 Grid

Fetteresso 132kV substation

NESO connection site, host SHET.

Contracted here0.50 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue496.7 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Fetteresso Wind Farm7 Nov 202530 Sep 202637 MW
Drumlithie Battery Storage31 May 202431 Oct 202849.9 MW
Craigneil Wind Farm22 Jul 202531 Oct 203042 MW
Fasque Windfarm31 May 202431 Oct 2031105 MW
GALILEO 12 LIMITED22 Jul 202531 Oct 2033150.8 MW
Colmealie Wind - Solar - BESS Farm22 Jul 202531 Oct 2037112 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2026: 37 MW2028: 87 MW2030: 129 MW2031: 234 MW2033: 385 MW2037: 497 MW202620282030203220342037497 MW
0 MW250 MW500 MW2026: 37 MW2028: 87 MW2030: 129 MW2031: 234 MW2033: 385 MW2037: 497 MW20262029203220352037497 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202637 MW
202886.9 MW
2030128.9 MW
2031233.9 MW
2033384.7 MW
2037496.7 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Fetteresso Wind Farm37 MW0 MW30 Sep 20261gate 1Awaiting Consents
2Drumlithie Battery Storage49.9 MW37 MW31 Oct 2028not statedgate not printedScoping
3Craigneil Wind Farm42 MW86.9 MW31 Oct 2030not statedgate not printedScoping
4Fasque Windfarm105 MW128.9 MW31 Oct 20311gate 1Scoping
5GALILEO 12 LIMITED150.8 MW233.9 MW31 Oct 2033not statedgate not printedScoping
6Colmealie Wind - Solar - BESS Farm112 MW384.7 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026137 MW
2028149.9 MW
2030142 MW
20311105 MW
20331150.8 MW
20371112 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
GALILEO 12 LIMITEDHybrid150.8 MW31 Oct 2033Scoping
Colmealie Wind - Solar - BESS FarmHybrid112 MW31 Oct 2037Scoping
Fasque WindfarmHybrid105 MW31 Oct 2031Scoping
Drumlithie Battery StorageBattery storage49.9 MW31 Oct 2028Scoping
Craigneil Wind FarmOnshore wind42 MW31 Oct 2030Scoping
Fetteresso Wind FarmOnshore wind37 MW30 Sep 2026Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.