The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Fiddes Battery Storage
31 May 2024 to 31 Oct 2028 (gate not printed) - Meetlaw BESS
31 May 2024 to 31 Oct 2031 (gate not printed) - Nether Pitforthie BESS
20 Dec 2024 to 31 Oct 2032 (gate 1) - GB-EU MPI
18 Mar 2025 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Fiddes Battery Storage | 31 May 2024 | 31 Oct 2028 | 30 MW |
| Meetlaw BESS | 31 May 2024 | 31 Oct 2031 | 49.9 MW |
| Nether Pitforthie BESS | 20 Dec 2024 | 31 Oct 2032 | 50 MW |
| GB-EU MPI | 18 Mar 2025 | 31 Oct 2033 | 1,800 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2028 | 30 MW |
| 2031 | 79.9 MW |
| 2032 | 129.9 MW |
| 2033 | 1,929.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Fiddes Battery Storage | 30 MW | 0 MW | 31 Oct 2028 | not stated | gate not printed | Scoping |
| 2 | Meetlaw BESS | 49.9 MW | 30 MW | 31 Oct 2031 | not stated | gate not printed | Consents Approved |
| 3 | Nether Pitforthie BESS | 50 MW | 79.9 MW | 31 Oct 2032 | 1 | gate 1 | Scoping |
| 4 | GB-EU MPI | 1,800 MW | 129.9 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2028 | 1 | 30 MW |
| 2031 | 1 | 49.9 MW |
| 2032 | 1 | 50 MW |
| 2033 | 1 | 1,800 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| GB-EU MPI | Interconnector | 1,800 MW | 31 Oct 2033 | Scoping |
| Nether Pitforthie BESS | Battery storage | 50 MW | 31 Oct 2032 | Scoping |
| Meetlaw BESS | Battery storage | 49.9 MW | 31 Oct 2031 | Consents Approved |
| Fiddes Battery Storage | Battery storage | 30 MW | 31 Oct 2028 | Scoping |
| Twinshiels (Tullo 2) Wind Farm | Onshore wind | 25 MW | not stated | Built |
| Brownieleys | Onshore wind | 7.5 MW | not stated | Built |
| Hillhead Of Auquhirrie Wind Generating station | Onshore wind | 6.9 MW | not stated | Built |
| Brotherton Wind Farm | Onshore wind | 4.6 MW | not stated | Built |
| Kempstone Hill Wind Generating Station | Onshore wind | 2.4 MW | not stated | Built |
Supported by National Energy SO Open Data