The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- SSE Fiddlers Ferry Battery Energy Storage
31 May 2024 to 12 Feb 2027 (gate 2) - Fiddlers Ferry BESS
31 May 2024 to 31 Oct 2027 (gate 2) - Penketh Hall Farm
31 May 2024 to 1 Sep 2027 (gate 1) - Fiddlers Ferry BESS
31 May 2024 to 31 Oct 2028 (gate not printed) - Fiddlers Ferry BESS
31 May 2024 to 31 Oct 2029 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| SSE Fiddlers Ferry Battery Energy Storage | 31 May 2024 | 12 Feb 2027 | 150 MW |
| Fiddlers Ferry BESS | 31 May 2024 | 31 Oct 2027 | 300 MW |
| Penketh Hall Farm | 31 May 2024 | 1 Sep 2027 | 249.9 MW |
| Fiddlers Ferry BESS | 31 May 2024 | 31 Oct 2028 | 300 MW |
| Fiddlers Ferry BESS | 31 May 2024 | 31 Oct 2029 | 300 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 699.9 MW |
| 2028 | 999.9 MW |
| 2029 | 1,299.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | SSE Fiddlers Ferry Battery Energy Storage | 150 MW | 0 MW | 12 Feb 2027 | 2 | gate 2 | Consents Approved |
| 2 | Fiddlers Ferry BESS | 300 MW | 150 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 3 | Penketh Hall Farm | 249.9 MW | 450 MW | 1 Sep 2027 | 1 | gate 1 | Scoping |
| 4 | Fiddlers Ferry BESS | 300 MW | 699.9 MW | 31 Oct 2028 | not stated | gate not printed | Consents Approved |
| 5 | Fiddlers Ferry BESS | 300 MW | 999.9 MW | 31 Oct 2029 | not stated | gate not printed | Consents Approved |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 3 | 699.9 MW |
| 2028 | 1 | 300 MW |
| 2029 | 1 | 300 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Fiddlers Ferry BESS | Battery storage | 900 MW | 31 Oct 2029 | Consents Approved |
| Penketh Hall Farm | Battery storage | 249.9 MW | 1 Sep 2027 | Scoping |
| SSE Fiddlers Ferry Battery Energy Storage | Battery storage | 150 MW | 12 Feb 2027 | Consents Approved |
Supported by National Energy SO Open Data