N84 Grid

Fiddlers Ferry 275kV Substation

NESO connection site, host NGET.

Contracted here1.30 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date12 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,299.9 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
SSE Fiddlers Ferry Battery Energy Storage31 May 202412 Feb 2027150 MW
Fiddlers Ferry BESS31 May 202431 Oct 2027300 MW
Penketh Hall Farm31 May 20241 Sep 2027249.9 MW
Fiddlers Ferry BESS31 May 202431 Oct 2028300 MW
Fiddlers Ferry BESS31 May 202431 Oct 2029300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2027: 700 MW2028: 1,000 MW2029: 1.3 GW2027202820291.3 GW
0 MW1.0 GW2.0 GW2027: 700 MW2028: 1,000 MW2029: 1.3 GW2027202820291.3 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027699.9 MW
2028999.9 MW
20291,299.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1SSE Fiddlers Ferry Battery Energy Storage150 MW0 MW12 Feb 20272gate 2Consents Approved
2Fiddlers Ferry BESS300 MW150 MW31 Oct 20272gate 2Consents Approved
3Penketh Hall Farm249.9 MW450 MW1 Sep 20271gate 1Scoping
4Fiddlers Ferry BESS300 MW699.9 MW31 Oct 2028not statedgate not printedConsents Approved
5Fiddlers Ferry BESS300 MW999.9 MW31 Oct 2029not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20273699.9 MW
20281300 MW
20291300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Fiddlers Ferry BESSBattery storage900 MW31 Oct 2029Consents Approved
Penketh Hall FarmBattery storage249.9 MW1 Sep 2027Scoping
SSE Fiddlers Ferry Battery Energy StorageBattery storage150 MW12 Feb 2027Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.