N84 Grid

Finstown (Orkney) GSP

NESO connection site, host SHET.

Contracted here0.14 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Apr 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue138.8 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Orkney Finstown Embedded Generation7 Nov 202530 Apr 202350 MW
Orkney Finstown Embedded Generation7 Nov 202531 Oct 202460 MW
Hammars Hill B7 Nov 202530 Jun 20288.4 MW
Hesta Head22 Jul 20256 Apr 202920.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2023: 50 MW2024: 110 MW2028: 118 MW2029: 139 MW2023202420252026202720282029139 MW
0 MW100 MW200 MW2023: 50 MW2024: 110 MW2028: 118 MW2029: 139 MW2023202520272029139 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202350 MW
2024110 MW
2028118.4 MW
2029138.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Orkney Finstown Embedded Generation50 MW0 MW30 Apr 2023not statedgate not printedScoping
2Orkney Finstown Embedded Generation60 MW50 MW31 Oct 2024not statedgate not printedScoping
3Hammars Hill B8.4 MW110 MW30 Jun 2028not statedgate not printedConsents Approved
4Hesta Head20.4 MW118.4 MW6 Apr 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2023150 MW
2024160 MW
202818.4 MW
2029120.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Orkney Finstown Embedded GenerationOnshore wind110 MW31 Oct 2024Scoping
Hesta HeadOnshore wind20.4 MW6 Apr 2029Scoping
Hammars Hill BOnshore wind8.4 MW30 Jun 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.