The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Fraserburgh Energy Plant
7 Nov 2025 to 31 Oct 2026 (gate 2) - Fraserburgh Energy Storage
7 Nov 2025 to 31 Oct 2027 (gate 2) - Tyrie Mains PV
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Fraserburgh GSP
7 Nov 2025 to 31 Oct 2026 (gate not printed) - Cairnbulg BESS
7 Nov 2025 to 31 Oct 2033 (gate not printed) - Boothby Road BESS (PI CS)
7 Nov 2025 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Fraserburgh Energy Plant | 7 Nov 2025 | 31 Oct 2026 | 45 MW |
| Fraserburgh Energy Storage | 7 Nov 2025 | 31 Oct 2027 | 40 MW |
| Tyrie Mains PV | 7 Nov 2025 | 31 Oct 2025 | 0.17 MW |
| Fraserburgh GSP | 7 Nov 2025 | 31 Oct 2026 | 0.2 MW |
| Cairnbulg BESS | 7 Nov 2025 | 31 Oct 2033 | 49.5 MW |
| Boothby Road BESS (PI CS) | 7 Nov 2025 | 31 Oct 2033 | 50 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 0.17 MW |
| 2026 | 45.37 MW |
| 2027 | 85.37 MW |
| 2033 | 184.87 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Fraserburgh Energy Plant | 45 MW | 0 MW | 31 Oct 2026 | 2 | gate 2 | Consents Approved |
| 2 | Fraserburgh Energy Storage | 40 MW | 45 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 3 | Tyrie Mains PV | 0.17 MW | 85 MW | 31 Oct 2025 | not stated | gate not printed | Scoping |
| 4 | Fraserburgh GSP | 0.2 MW | 85.17 MW | 31 Oct 2026 | not stated | gate not printed | Scoping |
| 5 | Cairnbulg BESS | 49.5 MW | 85.37 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 6 | Boothby Road BESS (PI CS) | 50 MW | 134.87 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 0.17 MW |
| 2026 | 2 | 45.2 MW |
| 2027 | 1 | 40 MW |
| 2033 | 2 | 99.5 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Boothby Road BESS (PI CS) | Battery storage | 50 MW | 31 Oct 2033 | Scoping |
| Cairnbulg BESS | Battery storage | 49.5 MW | 31 Oct 2033 | Scoping |
| Fraserburgh Energy Plant | Battery storage | 45 MW | 31 Oct 2026 | Consents Approved |
| Fraserburgh Energy Storage | Battery storage | 40 MW | 31 Oct 2027 | Consents Approved |
| Gowanfold Wind Generating Station | Onshore wind | 1.6 MW | not stated | Built |
| Fraserburgh GSP (Scottish Hydro Electric Power Distribution Plc) | Battery storage | 0.2 MW | 31 Oct 2026 | Scoping |
| Tyrie Mains PV | Solar | 0.17 MW | 31 Oct 2025 | Scoping |
Supported by National Energy SO Open Data