N84 Grid

Galashiels 132/33kV

NESO connection site, host SPT.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date2 Apr 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue114.6 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Leithenwater Wind Farm21 Mar 20252 Apr 203072.6 MW
Southern Upland Way Farm7 Nov 202531 Jul 203142 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2030: 73 MW2031: 115 MW20302031115 MW
0 MW100 MW200 MW2030: 73 MW2031: 115 MW20302031115 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203072.6 MW
2031114.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Leithenwater Wind Farm72.6 MW0 MW2 Apr 2030not statedgate not printedScoping
2Southern Upland Way Farm42 MW72.6 MW31 Jul 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2030172.6 MW
2031142 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Leithenwater Wind FarmHybrid72.6 MW2 Apr 2030Scoping
Southern Upland Way FarmBattery storage42 MW31 Jul 2031Scoping
Camieston FarmGas0.5 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.