The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Moorshield Wind Farm
7 Nov 2025 to 31 Oct 2026 (gate not printed) - Letham Farm BESS
7 Nov 2025 to 30 Jul 2027 (gate not printed) - Glasgow Road 40MW BESS
31 May 2024 to 31 Oct 2028 (gate not printed) - Giffnock GSP
7 Nov 2025 to 31 Oct 2033 (gate not printed) - Giffnock GSP
7 Nov 2025 to 31 Oct 2033 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Moorshield Wind Farm | 7 Nov 2025 | 31 Oct 2026 | 18 MW |
| Letham Farm BESS | 7 Nov 2025 | 30 Jul 2027 | 38 MW |
| Glasgow Road 40MW BESS | 31 May 2024 | 31 Oct 2028 | 40 MW |
| Giffnock GSP | 7 Nov 2025 | 31 Oct 2033 | 24.8 MW |
| Giffnock GSP | 7 Nov 2025 | 31 Oct 2033 | 19.8 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 18 MW |
| 2027 | 56 MW |
| 2028 | 96 MW |
| 2033 | 140.6 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Moorshield Wind Farm | 18 MW | 0 MW | 31 Oct 2026 | not stated | gate not printed | Scoping |
| 2 | Letham Farm BESS | 38 MW | 18 MW | 30 Jul 2027 | not stated | gate not printed | Scoping |
| 3 | Glasgow Road 40MW BESS | 40 MW | 56 MW | 31 Oct 2028 | not stated | gate not printed | Scoping |
| 4 | Giffnock GSP | 24.8 MW | 96 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 5 | Giffnock GSP | 19.8 MW | 120.8 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 18 MW |
| 2027 | 1 | 38 MW |
| 2028 | 1 | 40 MW |
| 2033 | 2 | 44.6 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Giffnock GSP (SP DISTRIBUTION PLC) | Hybrid | 44.6 MW | 31 Oct 2033 | Scoping |
| Glasgow Road 40MW BESS | Battery storage | 40 MW | 31 Oct 2028 | Scoping |
| Letham Farm BESS | Battery storage | 38 MW | 30 Jul 2027 | Scoping |
| Moorshield Wind Farm | Onshore wind | 18 MW | 31 Oct 2026 | Scoping |