N84 Grid

Giffnock 275/33kV

NESO connection site, host SPT.

Contracted here0.14 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue140.6 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Moorshield Wind Farm7 Nov 202531 Oct 202618 MW
Letham Farm BESS7 Nov 202530 Jul 202738 MW
Glasgow Road 40MW BESS31 May 202431 Oct 202840 MW
Giffnock GSP7 Nov 202531 Oct 203324.8 MW
Giffnock GSP7 Nov 202531 Oct 203319.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 18 MW2027: 56 MW2028: 96 MW2033: 141 MW20262027202820292030203120322033141 MW
0 MW100 MW200 MW2026: 18 MW2027: 56 MW2028: 96 MW2033: 141 MW2026202820302033141 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202618 MW
202756 MW
202896 MW
2033140.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Moorshield Wind Farm18 MW0 MW31 Oct 2026not statedgate not printedScoping
2Letham Farm BESS38 MW18 MW30 Jul 2027not statedgate not printedScoping
3Glasgow Road 40MW BESS40 MW56 MW31 Oct 2028not statedgate not printedScoping
4Giffnock GSP24.8 MW96 MW31 Oct 2033not statedgate not printedScoping
5Giffnock GSP19.8 MW120.8 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026118 MW
2027138 MW
2028140 MW
2033244.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Giffnock GSP (SP DISTRIBUTION PLC)Hybrid44.6 MW31 Oct 2033Scoping
Glasgow Road 40MW BESSBattery storage40 MW31 Oct 2028Scoping
Letham Farm BESSBattery storage38 MW30 Jul 2027Scoping
Moorshield Wind FarmOnshore wind18 MW31 Oct 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.